The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Centenary Way. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January.
Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year !
Monday, 23 December 2013
Friday, 29 November 2013
Friday, 25 October 2013
All internal work
this week has been suspended in the interest of health and safety as a clear and
safe access could not be provided in or out of the building. The reason for this
was the route that the gas and electric take to enter each unit runs along the
length of the front of the building and this was the work programmed in for
this week. At the start of the
week British Gas were on site and by mid week Northern power grid commenced
their share of the works required to get the building live. Next week we will
have light and heat and the internal work will continue.
Friday, 11 October 2013
Once the units which
had been plastered the previous week had had enough time to dry the decorators
were on site to prepare the units and then apply the mist
coat.
Once the mist coat
has dried the 2nd fix M&E can start, prioritising the kitchens and then
into the bathrooms. By working in this
sequence it free's up the next trade which is the joiners who start to fit the
kitchen units.
Externally this week
the bricklayers and renderers completed the front elevation, this then allowed the
scaffold to be stripped in preparation for the installation of services next
week.
Friday, 4 October 2013
Friday, 20 September 2013
With Autumn
approaching and the annual increase in fuel costs more than likely to be
announced in the coming weeks the insulation work being undertaken on Centenary Way over
the last two weeks seems extremely relevant.
The final job to
complete before the walls can be closed up is to double check that all relevant
areas are sealed and that ply pattresses have been firmly fitted to all required
areas to support the fixing of kitchen wall units, hand rails and
shelves.
Friday, 6 September 2013
Friday, 30 August 2013
Friday, 23 August 2013
Busy week both on and off site. The internals have been making good progress with each property starting to take shape with the completion of 1st fix dry lining the walls are now up giving a better feel for the proportions of each flat.
Once half the units had the internal walls up the 1st fix M&E started. Initially this is the mechanical work, vents for the MVHR units and pipe work for radiators, once half of the units are completed the 2nd half of the M&E team will commence work, the electricians.
Off site the progress has been steady with the drainage connection completed to the existing foul run, the main pipe from this is now being laid back towards site. In order to minimise disruption to the local community we are doing this in two half so we can keep the road open at all times. The plan is to complete it all before the schools start back after their summer holidays, we are in good shape to achieve this, as the first half is complete and the seconded half will be done next week.
Once half the units had the internal walls up the 1st fix M&E started. Initially this is the mechanical work, vents for the MVHR units and pipe work for radiators, once half of the units are completed the 2nd half of the M&E team will commence work, the electricians.
Off site the progress has been steady with the drainage connection completed to the existing foul run, the main pipe from this is now being laid back towards site. In order to minimise disruption to the local community we are doing this in two half so we can keep the road open at all times. The plan is to complete it all before the schools start back after their summer holidays, we are in good shape to achieve this, as the first half is complete and the seconded half will be done next week.
Friday, 16 August 2013
With all the offsite drainage ongoing it has been crucial that all the trades onsite have enough materials delivered before the road is closed. The manhole connecting into the existing foul run is now 90% complete and the pipe work from it heading back to site is 50% across the road.
Internals are moving steadily alone this week all the acoustic floors were completed and the first three units 1st fix drylining complete ready for M&E to start on Monday.
Internals are moving steadily alone this week all the acoustic floors were completed and the first three units 1st fix drylining complete ready for M&E to start on Monday.
Friday, 9 August 2013
The roof was completed this week.
Internals have started with the dry liners working through the units constructing the perimeter boards/internal walls. Once these are completed and sealed the joiner will start next week on the first floor installing the acoustic floors.
On the other side of centenary way the off site drainage began. First all existing service drawings were checked then the area was CAT scanned and marked out. Once we had located all the existing services and installed a temporary traffic light system work began on constructing the manhole furthest away from site. Over the next couple of weeks we will be working back into site.
Internals have started with the dry liners working through the units constructing the perimeter boards/internal walls. Once these are completed and sealed the joiner will start next week on the first floor installing the acoustic floors.
On the other side of centenary way the off site drainage began. First all existing service drawings were checked then the area was CAT scanned and marked out. Once we had located all the existing services and installed a temporary traffic light system work began on constructing the manhole furthest away from site. Over the next couple of weeks we will be working back into site.
Friday, 2 August 2013
Both the Roofers and Window fitters made a start on site at the beginning of the week. The roofers completed the felt and baton part of their work by Friday making the building water tight from above.
And all the windows were also installed making the building water tight so regardless of any summer showers at the weekend the internals start next week.
Friday, 26 July 2013
To capitalise on the speed of a Timber Frame build, which when all goes right the external works can progress in tandem along side the internals. However this all depends on the frame being kept dry and at this point we are not water tight. I may have jinxed it last week talking about the good weather as we did see some ominous looking clouds Monday, and then rain for a few hours Tuesday morning, luckily no thunder or lighting by the time the 50 ton crane had arrived ready for the final lift. The individual units roofs were lowered down to the ground, the first floor wall panels are then lifted up in place and constructed. The roof is then lifted back up and landed onto the awaiting wall panels. This process is then repeat for the remaining 4 first floor units.
By the end of the week the Timber frame stands complete, with the full perimeter scaffold around it and safety netting inside ready for the roofers on Monday.
With the help of a wet vacuum and some good fortune as the sun was back out by the end of the week our moisture levels are below where they need to be. We should be starting the internal perimeter boards late next week once we are water tight.Friday, 19 July 2013
As Iong as I can remember a few days of sun around this time of year gets called a hot weather spell or a heat wave, but its official this is called Summer. This week was another gloriously sunny one, and I'm please to say no one on site has complained and we don't seem to be slowing down. Progress has been good this week. On Tuesday another 35ton crane arrived on site along with the delivery of the roof trusses. The trusses were lifted up on top of the first floor where the joiners started to assemble the roof.
Friday, 12 July 2013
With prior submittal and approval of lifting plans Centenary Way had a 35 ton crane on site on two occasions this week, firstly to erect the ground floor wall panels.
Then on Friday which turned out to be the hottest day of the year the crane returned for the second time and the Timber Frame contractors erected the first floor cassettes.
Friday, 5 July 2013
With the gas proof membrane down the insulation was cut to size and laid at the start of the week and then the floor was poured. The base of the road inside site was also laid giving a clean and safe access up to the building ready for all trades working on the external envelope and internals. The scaffolders also made a start towards the end of the weeks in preparation for the Timber frame next week.
Friday, 28 June 2013
Subscribe to:
Posts (Atom)

