Once the units which
had been plastered the previous week had had enough time to dry the decorators
were on site to prepare the units and then apply the mist
coat.
Once the mist coat
has dried the 2nd fix M&E can start, prioritising the kitchens and then
into the bathrooms. By working in this
sequence it free's up the next trade which is the joiners who start to fit the
kitchen units.
Externally this week
the bricklayers and renderers completed the front elevation, this then allowed the
scaffold to be stripped in preparation for the installation of services next
week.