Friday, 11 October 2013

Once the units which had been plastered the previous week had had enough time to dry the decorators were on site to prepare the units and then apply the mist coat.


Once the mist coat has dried the 2nd fix M&E can start, prioritising the kitchens and then into the bathrooms. By working in this sequence it free's up the next trade which is the joiners who start to fit the kitchen units.
 

Externally this week the bricklayers and renderers completed the front elevation, this then allowed the scaffold to be stripped in preparation for the installation of services next week.