All internal work
this week has been suspended in the interest of health and safety as a clear and
safe access could not be provided in or out of the building. The reason for this
was the route that the gas and electric take to enter each unit runs along the
length of the front of the building and this was the work programmed in for
this week. At the start of the
week British Gas were on site and by mid week Northern power grid commenced
their share of the works required to get the building live. Next week we will
have light and heat and the internal work will continue.
Friday, 25 October 2013
Friday, 11 October 2013
Once the units which
had been plastered the previous week had had enough time to dry the decorators
were on site to prepare the units and then apply the mist
coat.
Once the mist coat
has dried the 2nd fix M&E can start, prioritising the kitchens and then
into the bathrooms. By working in this
sequence it free's up the next trade which is the joiners who start to fit the
kitchen units.
Externally this week
the bricklayers and renderers completed the front elevation, this then allowed the
scaffold to be stripped in preparation for the installation of services next
week.