All internal work
this week has been suspended in the interest of health and safety as a clear and
safe access could not be provided in or out of the building. The reason for this
was the route that the gas and electric take to enter each unit runs along the
length of the front of the building and this was the work programmed in for
this week. At the start of the
week British Gas were on site and by mid week Northern power grid commenced
their share of the works required to get the building live. Next week we will
have light and heat and the internal work will continue.