Friday, 25 October 2013

All internal work this week has been suspended in the interest of health and safety as a clear and safe access could not be provided in or out of the building. The reason for this was the route that the gas and electric take to enter each unit runs along the length of the front of the building and this was the work programmed in for this week. At the start of the week British Gas were on site and by mid week Northern power grid commenced their share of the works required to get the building live. Next week we will have light and heat and the internal work will continue.