Progress is ongoing with critical work being completed on time moving us ever closer to the arrival of the Timber Frame. This week the final part of the raft foundation was poured and the rain water gullies installed to the back of Plots 9 & 10.
The remaining top soil to the rear of the build was imported.
On Friday the remaining substructure block work was complete leaving the required time before the beam and block floor is installed mid next week.