The drainage to the rear of the building was completed this week and the ground levels prepared ready for the paving flags to be laid. It was also important this week to load out not only the paving flags needed to this elevation but to also load out the stone required to build up to the 1st scaffold lift. Once the remaining foundation is poured it wont be possible too access this area with heavy plant.